Site Progress | Diamond Ring Residencia
Young India Housing A Project By Young India Housing · 18+ Years · 14 Projects · ISO 9001:2015 View all projects →
Construction Updates

Site Progress

Follow construction at Diamond Ring Residencia. We post regular updates with photos and walkthrough videos so you can see the work on the ground.

Latest from the ground

Dated updates from our on-site team — construction milestones, approvals, and what's next.

  1. 19 June 2026

    Plots demarcated across the levelled layout

    The layout has been graded and levelled, and individual plots are now marked out with concrete boundary pillars and Young India Housing flags. On-site teams are raising the flag poles that line the internal roads — making the plot grid clearly readable on the ground.

    Levelled plot layout with a concrete demarcation pillar and Young India Housing flags at Diamond Ring Residencia
    Worker raising flag poles beside a freshly painted plot demarcation pillar at Diamond Ring Residencia
  2. 17 June 2026

    Compound wall rising along the boundary

    The concrete-block compound wall is going up along the project boundary, and electric poles have been erected alongside it — building out the perimeter and the power line that will serve the layout.

    Concrete-block compound wall rising along the boundary with an electric pole erected at Diamond Ring Residencia
  3. 15 June 2026

    Stormwater pipeline laid along the boundary

    Drainage crews are laying the stormwater pipeline in the trench that runs alongside the compound wall — extending the underground network that will carry run-off away from the internal roads.

    UPVC stormwater pipe laid in the trench alongside the compound wall at Diamond Ring Residencia
  4. 13 June 2026

    Road-edge kerbing and drainage chambers going in

    Along the graded internal roads, teams are setting road-edge kerb stones, the water main, and the RCC manhole chambers and pipes that form the drainage network — laying the groundwork for the road and utility layout across the project.

    Crew laying road-edge kerb stones and a water main along a graded internal road at Diamond Ring Residencia
    RCC manhole chamber and kerb stones being set along the drainage line at Diamond Ring Residencia
    RCC manhole rings and pipes laid in the drainage trench along the internal road at Diamond Ring Residencia
  5. 9 June 2026

    Drainage work under way across the layout

    On-site teams continue laying the underground drainage network across Diamond Ring Residencia — extending the storm-water and sewerage lines that run beneath the project's internal roads as the layout's groundwork advances.

  6. 6 June 2026

    Footpath work under way along the internal roads

    On-site teams are laying the footpaths that run alongside Diamond Ring Residencia's internal roads — adding the pedestrian edge to the project's road network as the layout's groundwork nears completion.

  7. 5 June 2026

    Pipeline work under way across the layout

    On-site teams are laying the underground pipeline network across Diamond Ring Residencia — extending the utility infrastructure that runs beneath the project's internal roads.

  8. 5 May 2026

    Entrance gate nearing completion

    DRR's signature entrance gate is in its final stages — finishing work continues on the gateway that defines the project's arrival experience.

  9. 4 May 2026

    Entrance arch under construction

    The entrance arch is taking shape — work continues on the project's signature gateway built atop the completed entrance gate pillars.

  10. 2 May 2026

    Drainage work continues on site

    Drainage installation work in progress — the on-site team continues laying the storm-water and sewerage network across the layout.

  11. 28 April 2026

    Entrance gate and front elevation

    Diamond Ring Residencia's entrance gate and front elevation captured on site.

    Entrance gate and front elevation at Diamond Ring Residencia
  12. 13 April 2026

    Drainage construction under way

    Drainage lines being laid across the site — a walkthrough plus close-up of the trench work.

    Drainage construction in progress at Diamond Ring Residencia
  13. 11 April 2026

    Transformer pillar under construction

    On-site work on the transformer pillar — the foundation for the project's dedicated power infrastructure.

    Transformer pillar construction in progress at Diamond Ring Residencia
    Transformer pillar construction in progress at Diamond Ring Residencia
  14. 15 March 2026

    Entrance gate pillars, compound wall plastering, and layout walkthrough

    Major progress on the entrance gate — concrete pillars are up and the compound wall has been fully plastered with iron railing fencing installed along the entire boundary. Inside the layout, all plots are marked with numbered pillars and colourful Young India Housing flags. Street light poles have been erected and a water tanker is on site for ongoing curing and road work.

  15. 14 March 2026

    Compound wall, fencing, and plot marking in progress

    Compound wall construction with iron railing and stone masonry is well underway along the boundary. Internal roads have been levelled and all plots are now marked with numbered boundary stones and colourful flags.

    Compound wall with iron railing and stone masonry at Diamond Ring Residencia
    Internal road with numbered plot markers and boundary flags at Diamond Ring Residencia
    Levelled road with plot boundary markers at Diamond Ring Residencia
    Full layout with flags marking all 61 plots at Diamond Ring Residencia
    Entrance area with compound wall and tree plantation at Diamond Ring Residencia